| The site of the
proposed extension is marked out. |
| The ground is excavated to a minimum of 600mm deep. Steel mesh is added and 150mm concrete poured in. |
| The inner leaf is built to floor level, the outer leaf to ground level. All drainage pipes are then added and covered with pea gravel. |
A
minimum of 100mm thick hardcore is then added and compacted. | ||
|
again this is compacted level. This is to prevent the damp proof membrane from puncturing. | optional 50mm insulation.Steel mesh is cut and set out ready for concrete. | ||
| The concrete is poured and screeded, it is then polished smooth using a large float. |
The
outer skin is then built to floor level using facing brick, the inner skin is then continued using block. | ||
|
The outer skin is then built to the same level as the inner skin inserting king span insulation. | are then continued to finished height. |
| WITH 30 YEARS BUILDING EXPERIENCE YOU KNOW YOU'RE IN GOOD HANDS |
| HOME |
House Build
Driveways
Garden Walls
Paving
Completed
Projects
Extension
Conservatory Bases
About Us
Contact Us
A-Z Glossary
Links
Copyright © 2005-2010 S. & G.Builders
All Rights Reserved.